Lagoon & Darwell Transmission Line Phase A

Lagoon & Darwell Transmission Line Phase A

 

 

 

 

 

 

Transmission Line Phase A (which includes Sandy Beach) UPDATE

A meeting took place April 18 2024 with the County advising scope and awaiting Alberta Environment approval on their end.  Sandy Beach attended merely for information.  To date no decision has been made on joining the project or not.  The County liaising with the Province on their end. 

Joint Lagoon Meeting: Wednesday Feb 15-2023 @ 7pm

Project scope and COST discussion

Sandy Beach Hall 63 Lakeshore Drive

Public Invited - please attend if you have input.

Your input is essential.

Council

 

Joint Lagoon Meeting: Tuesday Nov 8 @ 7pm 63 Lakeshore Drive

Public Invited - please attend if you have input.

Sandy Beach must inform the Commission of their intent by Nov 14.

Your input is essential.

 

Wastewater & Darwell Transmission Line Phase A - Update Tracker

Nov 3-2023 Meeting at the County - Barrhead to get involved in project and likely to upgrade from 12 million dollar project to just over 30 million dollars 90% grant funded by AT - the scope and MOU has changed now and Sandy Beach is staying informed on how the project will change now and what role SB has (if any - still tbd by Council) to play.

Sept 21-2023 (Report on Collection Systems)

Wastewater & Lagoon (Transmission Line Phase A) UPDATE for Jan 19-2023 meeting

Cost to Scope update Jan 18-2023

 

Item 5A Jan 19-2023 Phase A cost Update from Dec 14-2022 letter

Item 5D Wastewater Update for Dec 15-2022 (Nov 29 received)

Item 5B Deputy Mayor WASTEWATER UPDATE Report Nov 17-2022

LSAC Green infrastructure funding: Darwell Transmission Line

Transmission Line Cost projections Sept 2022

Letter to JLC on options forward March 12 2021

Item 6A OM Cost Darwell Reply March 9 2021

MH Reply on Lagoon Repair Options 1-4 March 2 2021

SV Reply Letter to Steering Committee Feb 25 2021

Item 6A Darwell Phase A Project Logbook Feb 2021

Deputy Mayor Report Feb 2021

2021 01 19 Letter To SVs

2020 12 17 Phase A Cost Summary

Logbook Update Nov 6 2020

Logbook Darwell Transmission Line Phase A

 

Updates

 

Lagoon

Update 2021

Scope of Work Nov 16-2021

Sept 30 Lagoon Report UPDATE

Update Nov 25, 2020

Item 6C MH Memo Lagoon Improvement Options 17 Nov 2020

JLC Nov 25 2020 memo/letter

January 2021

The Summer Villages have been asked to confirm commitment to the project by March 1 2021 and are seeking advice from Engineers on course for own lagoon as well as some extension to end of April to reply to Committee once feedback has been received on Water for Life and AWCCP grant applications for the lagoon.  A open house on the future of wastewater and costs associated is planned for the near future.  The website will be the ONLY source of information on this.

Oct 30, 2020

The Summer Villages of Sunrise Beach and Sandy Beach have requested that they have more time to evaluate the financial implications of this Project, therefore they will not be scheduling a meeting with the Town of Onoway in the near future to discuss and review the Wastewater Services Agreement and therefore immediate deliberation on the MOU and IA is on hold until further notice.

Sandy Beach will keep you advised on the status of the Project.

 

Darwell Transmission Line Phase A - Logbook

Discharge Notification June 1, 2020

AEP permission letter

ALL RESIDENTS - PUMP OUT RATES LETTER (2020)

The Discharge officially ended at the end of September 2019

Our Engineers has requested a new discharge or extension which has been approved.

The discharge is likely to start early June or July 2020 - same conditions apply as per PUBLIC NOTICE - the lagoon is off limits and the area is as per the map in the Public Notice.

Discharge in Process To START JUNE 2020

March 12th is a important Joint Lagoon Meeting as joining the transmission line and its proposed cost will be discussed as well as wastewater haul and fees in the area - the meeting is at 6 pm at the Sandy Hall.

 

Start Date:  23 June 2019

Completion:  Approx. 3-5 days from start date. 

For comments and to report any issues and concerns, please CONTACT: 

Tel: 780.967.2873 or email svsandyb@xplornet.ca 

PUBLIC NOTICE - 28 May 2019

The discharge application has now been approved and discharge will proceed according to the approved operational plan (see below) starting first week of June 2019.  Lakeshore Residents please take note.  ALL Residents or OTHER please note - The area south and west of the lagoon up to Lakeshore Drive (west) and the Lagoon Road (north) (public/municipal land) is OFF LIMITS and no activity or access is allowed under any circumstances.  The discharge process will take 2 weeks to complete.  Any persons in contravention or trespassing will be liable and trespass at THEIR OWN RISK and the municipality accepts no responsibility for any death, injury, illness or disability.   

PUBLIC NOTICE - 29 April 2019

Water well testing and sampling now complete April 23-2019 and submitted for parameter content and SAR testing to be submitted as part of discharge application

PUBLIC NOTICE - 23 March 2019

Sewage Lagoon Gypsum Application & Water Well Testing (click on blue description)

  1. Gypsum will be applied - March 23 all day;
  2. Water (well) testing will take place - in well areas on Lakeshore Drive
  3. Gypsum SDS

PUBLIC NOTICE - 5 March 2019

The lagoon discharge application has now been submitted to Alberta Environment Parks & Climate Change for approval - the attached operational plan on page 20 shows the discharge plan - residents on Lakeshore Drive please note the exact distribution - All residents and visitors caution - if the discharge is approved this area is off limits regardless mode of movement.  

Vegetation has been unaffected by earlier discharges and gypsum will be added to lagoon cells to reduce/break down the solid saline content in the cells in the hope of reducing SAR (saline content) and reducing the levels of the lagoon.  Alberta Environment has given written (see March 11 update above) permission to apply the gypsum PRIOR to the approval of the discharge application expressing hope that the gypsum application will be successful. 

Operational Plan Lagoon 2019

Update February 2019

the discharge application has now been submitted to AEPCC for approval - the attached operational plan on page 20 shows the discharge plan - residents on Lakeshore Drive please note the exact distribution - All residents and visitors caution - if the discharge is approved this area is off limits regardless mode of movement.  

Vegetation has been unaffected by earlier discharges and gypsum will be added to reduce saline content.

Operational Plan Lagoon 2019

Update Nov 2018

Proposed Sampling Locations 2018 (Nov) - 2019 

AEP is requiring the Summer Village to complete the requested soil testing and reports to proceed with an discharge approval.

Joint Lagoon Committee meeting minutes

2023

2022

2021

2020

2019

2018

Agendas

2021

2020

2019

2018